119 Surveys have shown that the primary skill needed to be a project manager is communication skill. The typical project manager spends approximately ______percent of his or her time communicating. A. 40-50

B. 50-60

C. 60-75

D. 75-90

E. 90-95

正确答案:D


95 A legally binding document offered unilaterally is a _____ .

A. purchase order

B. scope of work description

C. contract stipulation

D. level of effort proposal

E. request for proposal

正确答案:A


在你的项目中,你需要将成本归于发生成本的期间。为此,你应该

A. 识别项目组成成份以分配成本

B. 在成本预算中考虑项目进度

C. 准备详细和精确的成本估算

D. 准备成本执行计划

正确答案:A


费用预测的计算包括( )

A.EACACWPBACBCWP

B.EACBAC/CPI

C.EACACWPBAC/CPI

D.以上都是

E.A及B

正确答案:E


181 The critical path in a schedule network is the path that:

A. Takes the longest time to complete

B. Must be done before any other tasks

C. Allows some flexibility in scheduling a start time.

D. Is not affected by schedule slippage

E. All of the above

正确答案:A


项目管理师历年真题和解答8篇 第2篇


有效风险管理的首要要求是 ( )

A.决策所需信息的透明度高

B.风险所有关系明确

C.在管理已识别风险的过程中尽早的委任项目经理

D.受过风险培训并能理解风险起因的项目团队成员帮助创建和实施风险降低策略

正确答案:A


128 On a precedence diagram, the arrow between two boxes is called:

A. An activity.

B. A constraint. C. An event.

D. The critical path.

E. None of above

正确答案:B


In which of the following cost estimating techniques are statistics models used:

A . nonparametric cost estimating

B . parametric cost estimating

C . life cycle cost estimating

D . bottom-up estimating

E . All of the above.

正确答案:B


7 Using the situation stated in the Special window, what is the total price variance for direct material? A. $140.00

B. $736.00

C. $0.02

D. -$350.00

E. $5850.00

正确答案:B


102 Using the situation stated in the Special window, which WBS element has a favorable cost variance of $150?

A. Element P

B. Element Q

C. Element R

D. Element S

E. None of the above

正确答案:C


项目管理师历年真题和解答8篇 第3篇


106 Cost Reimbursable contracts are equivalent to:

A. Cost plus contracts

B. Fixed plus contracts

C. Progress payment contracts

D. Back charge contracts

E. None of the above

正确答案:A


165 Lessons learned are most often based upon project historical records. Lessons learned can be used to:

A. See what mistakes others have made

B. See how others have solved problems

C. Predict trends, highlight problems and identify alternatives

D. All of the above

E. A and B only

正确答案:D


The receiver filters messages based on all but the following:

A Language

B Distance

C Culture

D Knowledge

E Authority/Reputation

正确答案:B


95 Which percent of the total project labor hours are typically expended by the end of the second phase of the project life cycle?

A. 5%

B. 10%

C. 15%

D. 25%

E. 50%

正确答案:D


Work authorization forms are needed in order to:

AAuthorize line organizations to charge against the project

BEstablish an audit trail

CDevelop a structured methodology for release of funds

DAll of the above

EA and C only

正确答案:D
D


项目管理师历年真题和解答8篇 第4篇


130 What is the relative priority of project Cost, Schedule and Quality?

A. 1)Cost - 2)Schedule - 3)Quality

B. 1)Quality - 2)Schedule - 3)Cost

C. 1)Quality - 2)Cost - 3)Schedule

D. 1)Schedule - 2)Quality - 3)Cost

E. All are of equal priority

正确答案:E


154 _____ is associated with a buyer's request for materials or equipment to meet a particular need or accomplish a specific purpose.

A. Express warranty

B. Implied warranty of merchantability

C. Implied warranty of fitness for a particular purpose

D. Prescribed warranty

E. None of the above

正确答案:C


当一项流程被为是处于控制之下的时候,它:

A、不应该被调整

B、不能通过对其进行调整以达到某些方面的改进

C、能表现出由于预料到的原因或正常原因引起的差异

D、不能因为任何原因而进行审查或返工

正确答案:A


一次项目检查发现你的项目有不能按时完成的风险。有些项目需要使用同一资源,这就导致严重的资源冲突。你必须定量分析项目的风险,并确定怎样为成本和进度意外情况做准备。你用蒙特?卡罗分析方法来进行进度风险分析。你的进度风险分析的基础是—( )

A.WBS

B.甘特图

C.PDM进度计划

D.可能性/影响等级评估矩阵

正确答案:C


Your client, with which you have good relations, wants you to provide him with office supplies. This task is not supported under your contract. You respond to your client's informal request using which medium?

A Speech

B Written

C Oral

D A and C

E Form. letter

正确答案:C


项目管理师历年真题和解答8篇 第5篇


156 Deflection involves the transfer of risk by:

A. Contracting out to another party

B. Developing schedule alternative.

C. Establishing functions under the project manager to handle risk events.

D. Disaster planning and responses.

E. None of the above

正确答案:A


For effective communication, the message should be oriented to the _____.

A Initiator

B Receiver

C Media

D Management style

E Corporate culture

正确答案:B


38 Deflection involves the transfer of risk by:

A. Contracting out to another party

B. Developing schedule alternative.

C. Establishing functions under the project manager to handle risk events.

D. Disaster planning and responses.

E. None of the above

正确答案:A


在谈判中最常出现的沟通问题是( )

A.一方曲解了对方所表达的内容

B.一方可能屈服于对方的立场

C.一方可能有意使对方迷惑

D.一方可能过于关注以下要讲什么而没有听见对方的发言

正确答案:A


资源计划编制的目的在于:

A、 确定执行项目活动所需的物理资源

B、 近似的计算完成项目活动所需的资源成本

C、 确定可能获取的资源

D、 评估组织有关项目使用资源的政策

正确答案:A


项目管理师历年真题和解答8篇 第6篇


一项资产的残值是( )

A.一项新资产被闲置时的价值

B.一年折旧期过后入帐的资产价值

C.项目当前已有的沉没成本

D.在一个资产有效寿命结束之日的期望价值

正确答案:D


Which of the following impacts the critical path?

A.Changing the task duration.

B.Reduce the free float of an activity.

C.Executing a backward pass

D.A or B

E.None of the above.

正确答案:A
A


The three most common types of project cost estimates are:

A . Order of magnitude, parametric, and budget.

B . Parametric, definitive and top down.

C . Order of magnitude, definitive and bottom up.

D . Order of magnitude, budget and definitive.

E . Analogy, parametric and top down.

正确答案:D


The contractual statement of work (CSOW)

A.Must be the same as the proposal statement of work

B.Does not identify reporting requirements

C.Can be at a different level of detail (i.e. WBS level) than the proposal statement of work

D.Identifies the contractor's organizational structure for the project

E.All of the above

正确答案:C
C


31 Cost forecasting calculations include:

A. EAC = ACWP + (BAC - BCWP)

B. EAC = BAC/CPI

C. EAC = ACWP + (BAC/CPI)

D. All of the above.

E. A and B

正确答案:E


项目管理师历年真题和解答8篇 第7篇


在项目执行中进度和成本执行绩效令人满意这时指派了一名新的项目经理他正在参加见面介绍会最重要的是什么( )

A.设定目标

B.向项目干系人介绍项目队伍成员

C.检查沟通

D.项目章程

正确答案:C


对一个项目使用项目管理技术的程度主要由项目的和决定的 ( )

A.预算进度

B.质量及进度要求

C.项目所处行业类型及规模

D.性质规模

正确答案:D


项目经理想向管理层显示可视的质量控制对过程的影响。完成它最好的工具是:

a. Pareto 图

b. 柱状图

c. 流程图

d. 控制图

e. 统计样本

正确答案:D
d [控制图用于显示结果、超时和过程是否被控制。]


104 Methods and techniques used to examine cost and technical data are called feasibility studies. The economic aspects of a feasibility study include interest rates, present worth factors, operating costs, depreciation and _____.

A. Capitalization costs.

B. Technical skill requirements.

C. Technology forecasting.

D. Strategic marketing intelligence.

E. All of the above.

正确答案:A


Which type of contract requires that the buyer keep the tightest labor/material cost control?

A Cost Plus Incentive Fee

B Cost Plus Percentage of Costs

C Cost Plus Fixed Fee

D Firm Fixed Price

E Firm Fixed Price Plus Incentive

正确答案:B


项目管理师历年真题和解答8篇 第8篇


以下哪个公式能最准确的计算活动历时 ?

A、 AD(活动历时)=工作数量/生产率

B、 AD=工作数量/资源数量

C、 AD=生产率/工作数量

D、 AD=生产率*工作数量/资源数量

正确答案:A


195 Techniques that can improve communication include:

A. establishing a single, one-way communications channel

B. avoiding face-to-face communication

C. using redundancy (i.e. saying it two different ways) whenever possible

D. disregarding the sensitivity of your receiver

E. All of the above

正确答案:C


当记录到实际测量到的质量特征时,如用千分之一英寸表达尺寸,质量是用什么来表示的?

A、 特性

B、 变量

C、 属性

D、 性质

正确答案:B


133 Using the WBS shown in the Special window, a typical work package would be:

A. Software development

B. Systems design

C. Coding

D. A, B, and C

E. None of the above

正确答案:E


Which of the following are types of status reports?

Adocument, variance, trend and exception

Bcost, trend, schedule and acquisition

Ccost, schedule, technical performance

Danalysis, cost, performance and schedule

EAll of the above.

正确答案:C